Site Observation Report #6

 

Project Name:  Emory Johns Creek Hospital:  Registration / Pre-Admissions Testing / Chapel

Project Address:  6300 Hospital Parkway, Johns Creek, GA 30097

Date of Observation:  Tuesday, 17 May 2016

Weather:  Partly Cloudy, 80°F

Time:  1:15 pm

 

Attendees:

Kevin Pittman, Cork-Howard Construction Co.

Erik Frandsen, Frandsen Architects, PC

Brittany Cencula, Frandsen Architects, PC

 

Work In Progress

-  Metal stud framing construction.

 

General Notes

-  Negative air has been setup for the construction area. 

-  Air filter machine setup and is exhausting out of rear aluminum framing window.

-  Removal of existing concrete curb at new door openings.

 